Full Application Workflow

The complete lifecycle of a labour registration application from Form 1 to Certificate issuance.

Workflow Diagram

The diagram below shows every stage an application passes through, including shortfall loops at the DEO and BOCW stages.

Fill Form 1
Draft
Pay Challan
PendingPayment
Payment Done
Paid
Submit to DEO
SubmittedToDEO
DEO Reviews
SubmittedToDEO
If satisfied → Forward to BOCW
DEO Shortfall
DEOShortfall
Architect Responds
Re-submits
Back to DEO
BOCW Reviews
SubmittedToBOCW
If satisfied → Forward to LEO
BOCW Shortfall
BOCWShortfall
Architect Responds
Re-submits
Back to BOCW
LEO Reviews
SubmittedToLEO
RDC Reviews
SubmittedToRDC
Approved
Approved
Certificate Issued
Architect downloads

All Statuses in Order

#StatusWho ActsDescription
1 Draft Architect Form 1 is being filled. Not yet submitted.
2 PendingPayment Architect Form 1 submitted. Challan generated. Awaiting payment.
3 Paid Architect Challan paid. Ready to submit to DEO.
4 SubmittedToDEO DEO Application submitted to DEO. Awaiting DEO review.
5a DEOShortfall Architect DEO returned application with shortfall. Architect must respond.
6 SubmittedToBOCW BOCW DEO forwarded to BOCW. Awaiting BOCW review.
6a BOCWShortfall Architect BOCW returned application with shortfall. Architect must respond.
7 SubmittedToLEO LEO BOCW forwarded to LEO. Awaiting LEO review.
8 SubmittedToRDC RDC LEO forwarded to RDC. Awaiting final approval.
9 Approved RDC approved. Registration Certificate issued. Process complete.

Key Rules of the Workflow

Typical Timeline

StageTypical DurationNotes
Form 1 + PaymentSame dayArchitect-controlled
DEO Review1–3 working daysMay vary by workload
BOCW Review2–5 working daysMay vary by workload
LEO Review2–3 working daysMay vary by workload
RDC Approval2–5 working daysFinal stage
Total (no shortfalls)~7–16 working daysEstimate only
Shortfalls add time to the process. Submitting a complete, accurate application with all required documents from the start is the best way to minimise delays.